Miele PDR 918 Commercial Tumble Dryers Installation Guide

Miele PDR 918 Commercial Tumble Dryers

Installation requirements

The tumble dryer must only be installed and commissioned by Miele Customer Service Department or an authorized dealer.

  • The tumble dryer must be installed in accordance with all relevant regulations and standards.
  • The dryer must only be operated in a room that has sufficient ventilation and which is frost-free.

Electrical connection

The electrical connection must be established by a qualified electrician.

  • The electrical connection may only be made to an electrical system provided in accordance with all appropriate local and national legislation, regulations, and guidelines. Please also observe the regulations set out by your insurance provider and energy supplier, accident prevention regulations, as well as recognized codes of practice.
  • The reliable and safe operation of this tumble dryer is only ensured if it has been connected to the mains electricity supply.

The required supply voltage, power rating, and fuse rating can be found on the data plate on the tumble dryer. Ensure that the supply voltage matches the voltage quoted on the data plate before establishing the electrical connection to the tumble dryer. Connection to a supply voltage other than the one quoted on the data plate can damage the tumble dryer if the voltage is too high.

  • If more than one voltage is specified on the data plate, the tumble dryer can be converted for connection to the relevant input voltage. This conversion must be performed by the Miele Customer Service Department or by an authorized dealer. During the conversion, the wiring instructions given on the wiring diagram must be followed.

The tumble dryer can either be hard-wired or connected using a plug-and-socket connection in accordance with IEC 60309-1. For a hard-wired connection, an all-pole isolation device must be available at the installation site. An isolation device is a switch that ensures a contact opening of more than 3 mm. These include circuit breakers, fuses, and contactors (IEC/EN 60947). If the mains supply cannot be permanently disconnected, the isolation device (including plug and socket) must be safeguarded against being switched on either unintentionally or without authorisation.

Tip: We recommend connecting the tumble dryer to the power supply via a plug and socket so that it is easier to conduct electrical safety checks (e.g. during maintenance or repair work).

  • The tumble dryer must not be connected to devices such as timers which would switch it off automatically.

If local regulations require that a residual current device (RCD) is installed, a type B residual current device (sensitive to universal current) must be used.

Steam connection

The steam connection must only be carried out by a registered installation technician. The information from the data plate, the wiring diagram and the documentation accompanying the appliance must be noted and complied with when connecting steam-heated Miele ap-pliances.

Condensate connection

The condensate separator must be installed so that when the system is not operating, the heater bank is completely emptied. This means that no condensate may remain in the heater bank. The installation of an inverted bucket condensate trap is recommended.

Air intake/exhaust air

The tumble dryer may only be operated when the ducting has been connected properly and the room is sufficiently ventilated.

  • Accessory parts may only be fitted when expressly approved by Miele. If other parts are used, warranty, performance and product liability claims will be invalidated.

Dimensions

Dimensions quoted in millimeters

Installation

Dimensions quoted in millimeters

  1. EL Electrical connection
  2. D Steam connection
  3. K Condensate connection
  4. AL Exhaust duct
  5. ZL Air intake
  6. PA Connection for equipotential bonding (optional)
  7. XCI XCI Box/Connector Box (optional

Installation (standard/on concrete plinth)

Dimensions quoted in millimeters

  1. B Drill hole/anchor point
  2. BS Concrete plinth

Technical data

Voltage variants/electrical data

Standard connection

  1. Supply voltage 1N AC 230 V
  2. Frequency 50/60 Hz
  3. Power rating 0.6 kW
  4. Fuse rating (on site) 10 A
  5. The minimum cross-section for connection cable 3×1.5 mm²
  6. Cable gland M20

Steam connection

  • Steam overpressure 600–1000 kPa
  • Boiling point 165–184 °C
  • Mass flow, peak capacity 35 kg/h
  • On-site threaded union for steam (internal thread) ½” mm
  • Length of steam valve connection cable 500 mm

The steam valve, dirt filter and steam shut-off valve must be fitted by the customer on site. The steam valve must be fitted in the direct vicinity of the steam connection.

Condensate connection

  1. On-site threaded union (internal thread) ½” mm

Shut-off equipment and condensate trap must be fitted by the customer on site.

Exhaust air

  1. The maximum nominal volume flow rate in extraction mode (PDR 9xx only) 715 m³/h
  2. Maximum nominal volume flow rate (PDR 5xx only) 550 m³/h
  3. The maximum permitted pressure loss of 200 Pa
  4. Connector on machine side (external diameter) 150 mm
  5. Connection pipe provided on-site (internal diameter) 150 mm
  6. Maximum exhaust air temperature 80 °C

As relative humidity inside the exhaust ducting can be as high as 100 %, suitable measures must be taken to prevent a backflow of condensate into the machine.

Air intake

Standard connection: air intake from the installation site

  • Recommended free air intake cross-section into the room: (equivalent to 3 times the exhaust air cross-section of a machine). 531 cm²
  • There must be sufficient air intake to the installation site to match the air outlet volume.
  • Alternative connection: air intake connection directly from outdoors
  • Connection sleeve on machine side (internal diameter) 161 mm
  • Connection pipe provided on-site (external diameter) 160 mm

Removing the protective cover exposes live parts. For safety reasons, a pipe must be installed from the tumble dryer’s central fresh air intake (over a minimum length of 900 mm) and secured with 2 screws.

Machine data  
Machine width, total 906 mm
Machine height, total 1400 mm
Machine depth, total 1035 mm
Niche width 1250 mm
Recommended wall spacing (up to the front edge of the machine) 1500 mm
Minimum wall spacing (up to the back edge of the lid) 500 mm
Packaging width 1090 mm
Packaging height 1526 mm
Packaging depth 1125 mm
Maximum gross volume 1871.3 l
Maximum gross weight 221.3 kg
Maximum net weight 207.5 kg
Max. floor load in operation 2300 N
Diameter of exhaust duct 150 mm
Drum diameter 850 mm
Diameter of drum opening 520 mm
Drum depth 613 mm
Drum volume 325 l
Diameter of door opening 520 mm
Maximum door opening angle 180°
Emission sound pressure level 50 dB(A) re 20 µPa
Sound power level 61
Average heat dissipation rate into the room 4.5 MJ/h
Permissible ambient temperature range 2–40 °C
Fixing options  
Fixing without plinth  
Quantity Screw size
Tensioning strips                                                                                                                                     2  
Wood screws DIN 571 (Ø × length)                                                                                                       2 6×40 mm
Plugs (Ø × length)                                                                                                                                 2 10×50 mm
Fixing the appliance in place is absolutely essential.

Fastenings for floating screed must be supplied by the customer on site.

 
Fixing to concrete plinth  
Quantity Screw size
Tensioning strips                                                                                                                                     2  
Wood screws DIN 571 (Ø × length)                                                                                                       2 6×40 mm
Plugs (Ø × length)                                                                                                                                 2 10×50 mm
If the tumble dryer is being fixed to a concrete plinth on site, fixing in place is absolutely essential. Fastenings for floating screed must be supplied by the customer on site.  

Options/Accessories

Concrete base (on-site)

  • Minimum width 900 mm
  • Recommended height 100 mm
  • Minimum height 50 mm
  • Minimum depth 1100 mm

The quality of the concrete and its strength must be assessed according to the machine load. The on-site concrete plinth must be fixed adequately to the floor.